VV Building B and C Elevator Renovations

STAFF REPORT


The elevator in Building B, and C at the Valle Verde Campus will be shut off from March 11 to the 29. The shutdown has been strategically schedule to minimize the impact for student, faculty, and staff.


This is following the completion of the elevator renovation at VV Building A.

 

This elevator outage will allow the Physical Plant to modernize the elevators with new wiring at the cab, wiring in the machine room, door sensors, door operators, controller, and electrical power unit. The completion of this project will provide Building B, & C at the Valle Verde Campus with an upgraded elevator. These improvements will greatly reduce the chance of unplanned breakdowns and minimize lead time to acquired materials needed at that time in the future.

 

We ask that all students, faculty and staff plan accordingly to use other means of egress to their destinations. Please do not attempt to enter the elevator during this period. The elevator will be out of order during the modernization period.

 


Temporary drop off/pick up locations and alternate routes for elevator access.


Building B

Modernization Starts on 03/11/24

Duration 1 week

Estimated Completion 03/16/24

 

Building C

Modernization Starts on 03/11/24

Duration 3 weeks

Estimated Completion 03/29/24

 


Temporary drop off/pick up locations and alternate routes for elevator access.


Any questions regarding this scheduled outage can be addressed directly to Roberto Samaniego (915) 831-7885 or Cesar Aguirre (915) 831-7765 at the Physical Plant department.